The North Face Jacket Breast C

daub rooms on the ground floor ceiling of the entrance

This Saturday we must completely remove the two rooms on the ground floor with Manu and Michel can begin to make the daub. We have also installed a small scaffold to facilitate work on the ceiling:


On the southwestern room on the other hand there is a little more work:
  • A plate of insulating plasterboard had separated. It was therefore necessary to remove it and then crop insurance (see photo below)

  • joints between plates are not made so it is necessary to work before they can begin making the daub ...